Datacentre Powerdraw and Heat Calculator

Size a GPU build against real datacentre sites, and see how they connect to the grid. Starting with Victoria, expanding statewide and then countrywide. Hardware baselines: NVIDIA DGX H100/H200 user guide (10.2 kW per node, 38,557 BTU/hr, 1105 CFM), NVIDIA DGX GB rack guide (~120 kW per GB200 NVL72 rack) and HPE GB300 NVL72 datasheet (132-140 kW per rack). Grid data: AEMO 2026 ISP, VicGrid, DataVic (compiled October 2026).

Text size: 100%

Step 1: Pick a site

Step 2: Configure your build

Presets: 0.1 near-zero (CDC/Southgate) / 2 liquid-cooled / 10 cooling-tower air

Large industrial contract in Victoria: roughly 0.05-0.13 AUD/kWh

Map: sites, powerline routes and substations

Operating Under construction Planned Proposed Substation Selected site powerline route Transmission line

Pipeline overview

Datacentre pipeline. Each row lists a site, its status, its capacity in megawatts of IT load, and a bar showing relative size.
Site Status Capacity (MW) Relative size